COMBINED CYCLE POWER PLANT ERBIL
In July 2012, Mass Group Holding has started converting its 1.000 MW Erbil Independent Power Project (IPP) from simple-cycle to combined-cycle technology. The present power plant is equipped with eigth 9E GE-gas turbines with a capacity of 1.000 MW and is Iraqi Kurdistan’s largest power plant. It will be converted to combined-cycle by additional eight HRSG’s and two GE-steam turbines, which will produce an additional extra power of 470 MW with the same gas amount.
On behalf of Mass Group Holding, APPA Consult GmbH is rensponsible for Owner`s Engineering works. Within the team of APPA, convex ZT GmbH is responsible for civil design works and convex Ltd. Şti. was responsible of supervising the civil works on site.
owner:
Mass Group Holding Ltd.
general Contractor:
APPA Consult GmbH
capacity (electrical):
470 MW
-
Photos:
APPA